Current active project

Parking Canopy Design

Design and tender preparation for shade canopies over existing parking areas on parcels 190 and 491.

Location
Agioi Omologites, Nicosia
Current phase
Preliminary / Concept Design & Tender Basis

PROJECTS

Current work

One active project is currently part of the Parking Projects hub.

Active project

Parking Canopy Design

Preliminary design and tender preparation for rectilinear steel shade canopies while retaining the existing parking layout and access.

Location
Agioi Omologites, Nicosia
Phase
Preliminary / Concept Design & Tender Basis
View project overview

Additional parking projects can be added to this hub in the future.

PARKING CANOPY DESIGN

Project overview

Four working areas, each linked to its authoritative project documentation.

SITE & PARKING LAYOUT

Existing operation retained

The project covers parcels 190 and 491. The existing parking layout is retained; parcel 491 is treated as two independent sub-parking areas, and access and manoeuvring must remain functional.

Open site data

CANOPY DESIGN

Rectilinear Γ and Τ systems

Confirmed requirements use Γ canopies for single rows and Τ canopies for double rows, with galvanized structural steel, perforated shade fabric, 2.40 m minimum clear height, no photovoltaics and no gutters.

Working assumptions: concept geometry and module dimensions remain preliminary and require design development.

STRUCTURAL DESIGN

Basis identified; sizing pending

Design is based on applicable Eurocodes and Cyprus National Annexes. Wind is considered a critical action; structural sizing and foundation design remain pending. Preliminary assumptions are not final design.

Open design basis

TENDER & PROCUREMENT

Performance-led public tender

The procurement approach uses performance-based specifications, supplier and brand neutrality, and technically equivalent solutions. The BOQ and tender package are future project outputs.

Open procurement strategy

CURRENT STATUS

Project status

Source of truth: PROJECT_STATUS.md
Current phase Preliminary / Concept Design
Current focus Typical Γ and Τ geometry
Status of Parking Canopy Design project work items
Project item Status
Site data 190 / 491Confirmed
Existing parking layoutConfirmed
Canopy concept Γ / ΤConfirmed
Steel / shade-fabric conceptConfirmed
Design basisInitial
Eurocodes + Cyprus NAIdentified
Typical Γ geometryNext
Typical Τ geometryNext
Wind / load calculationsPending
Structural sizingPending
FoundationsPending
DrawingsPending
Technical specificationsPending
BOQ / tender packagePending

NEXT STEP

Define the typical canopy geometry

Define the typical Γ and Τ canopy geometry and begin preliminary structural checks.

View current status

OPEN ITEMS

Design-development inputs

  • Final shade-fabric performance data
  • Market-available steel sections and lengths
  • Soil and foundation parameters
  • Site verification before construction
  • Underground services before foundation finalization

These are legitimate design-development items to be confirmed, not finalized project data.

KEY DECISIONS

Established project direction

Open decisions log

DOCUMENTS

Authoritative project documentation

The dashboard summarizes these files; the repository documentation remains the source of truth.